Procurement

Transformer sizing calculator

Enter the load, the voltages and the construction. The calculator returns the standard rating, the currents and the loss ceiling, and sends the result to the quote form with every value filled in.

The load
The share of the connected load that runs at the same time
The highest continuous loading you want the unit to run at

The rating

1250 kVA

Apparent power needed
1,039 kVA
Loading at that rating
83 %
Rated current, secondary
1,804 A400 V
Rated current, primary
65.6 A11 kV
Next incomer frame
2,000 A
Upper bound of the fault contribution
30.1 kAuk 6 %
Real power at rated current
1,125 kWPower factor 0.9
EU loss ceiling
Pk ≤ 9,500 WP0 ≤ 855 W
Next rating up
1600 kVA

kVA = kW × diversity × (1 + growth) ÷ power factor ÷ loading limit, then the next step of the standard series. Currents are S ÷ (√3 × U). The fault figure is the rated current divided by the impedance with an infinite upstream source.

Arithmetic on your inputs and on the standard series, not a design. The responsible engineer confirms the rating, the impedance and the protection, and the network operator confirms the connection. Availability, manufacturer, price and delivery are confirmed per project in a quotation.

How the rating is worked out

The connected load is multiplied by the diversity factor, because the loads on a site rarely all run at once. Planned growth is added, and the result is divided by the power factor to turn kilowatts into kilovolt amperes. Dividing once more by a loading limit below 100 percent leaves headroom the unit never uses in normal service.

The rating chosen is the next step of the standard series at or above that figure. Choosing a value between two steps usually costs more and takes longer without a technical gain, which is why the calculator never proposes one.

Transformer sizing chart for common loads

LoadAt power factor 0.8At 0.9At 0.95
100 kW125 kVA, 160 kVA111 kVA, 160 kVA105 kVA, 160 kVA
200 kW250 kVA, 250 kVA222 kVA, 250 kVA211 kVA, 250 kVA
300 kW375 kVA, 400 kVA333 kVA, 400 kVA316 kVA, 400 kVA
500 kW625 kVA, 630 kVA556 kVA, 630 kVA526 kVA, 630 kVA
750 kW938 kVA, 1000 kVA833 kVA, 1000 kVA789 kVA, 800 kVA
1,000 kW1,250 kVA, 1250 kVA1,111 kVA, 1250 kVA1,053 kVA, 1250 kVA
1,500 kW1,875 kVA, 2000 kVA1,667 kVA, 2000 kVA1,579 kVA, 1600 kVA
2,000 kW2,500 kVA, 2500 kVA2,222 kVA, 2500 kVA2,105 kVA, 2500 kVA

Each cell is the apparent power needed and the standard rating that carries it, with no diversity, growth or loading limit applied. The calculator applies those.

What the calculator does not decide

QuestionWho settles it
Motor starting and the voltage dip it causesThe designer, with the starting method of the largest motor
Harmonic loading from drives, UPS or invertersThe designer's harmonic assessment, which can change the specification
Impedance, vector group and tapping rangeThe designer and the network operator
Ambient temperature, altitude and enclosure deratingThe designer, with the manufacturer's datasheet
Whether the connection can take the loadThe network operator

From the result to a quotation

The request button carries the rating, the voltage pair, the frequency, the construction, the installation and a summary of the sizing into the quote form. Nothing is sent until the form is submitted. Daverlan then checks the specification, raises anything missing, and puts it to manufacturers whose published range covers it.

A specification sheet can also be copied or printed from the result, for a tender or for the engineer who signs the design.

Common questions

What size transformer do I need for a 200 kW load?

At a power factor of 0.8 a 200 kW load needs 250 kVA, and at 0.9 or 0.95 it still sits under 250 kVA. With 80 percent as the loading limit the answer moves to 315 kVA. The calculator shows both once the loading limit is set.

Is the result a design?

No. It is arithmetic on the inputs and the standard series. The responsible engineer confirms the rating against motor starting, harmonics and ambient conditions, and the network operator confirms the connection.

Why does the calculator ask for the construction?

Because the EU loss ceilings differ between liquid immersed and cast resin units, and because the construction decides where the unit can stand. The ceiling shown is the legal maximum for the rating, not the value of a particular unit.

Related

Send us the requirement

Send the rating, the voltage and the destination, or submit the specification, drawing or nameplate. Anything missing is raised before it reaches a supplier.