Switchgear

Ring main units (RMU) for 11 kV to 22 kV networks

Compact medium voltage switchgear for secondary distribution, with switches for the incoming and outgoing ring cables and a protected feeder for the transformer.

At a glance

Common rated voltages
12 kV and 24 kVfor 10 or 11 kV and 20 or 22 kV networks
Common configuration
two ring switches and a transformer feederextensible units add functions
Transformer protection
switch fuse or circuit breaker with relayset by the rating and the protection scheme
Insulation
gas, air or solidEU F gas rules apply from 2026 up to 24 kV
Standard
IEC 62271-200metal enclosed switchgear above 1 kV to 52 kV
Outline drawing for orientation.Not a photograph of a specific unit. Arrangement, enclosure and dimensions depend on the unit offered.

A ring main unit sits where a medium voltage cable ring meets a transformer. Two switches connect the incoming and outgoing ring cables, so the ring can be opened and closed around a fault, and a third function protects the transformer. The unit is compact, often sealed, and usually installed inside a compact or package substation.

The transformer protection function is the main choice. A switch fuse combination suits smaller transformers. A circuit breaker with a protection relay suits larger ratings and schemes that need more selective protection. Whether the unit is extensible, with functions that can be added later, is worth deciding at the outset.

What gets specified

ParameterTypical optionsWhat decides it
Rated voltage12 kV or 24 kVThe network voltage
ConfigurationRing switches and transformer feeders, fixed or extensibleThe network arrangement and future needs
Transformer protectionSwitch fuse or circuit breaker with relayTransformer rating and protection scheme
Insulation mediumGas, air or solidFootprint, environment and destination rules
OperationManual, or motorised for remote controlNetwork automation plans
Cable connectionBushing type and number of cables per functionThe cables used on the network
Internal arc classificationAs proven by type testWhere the unit stands
Fault indication and monitoringFault passage indicators, remote terminal unitNetwork automation

Typical options are the ones buyers most often specify. They are not a list of what is available, which is confirmed per enquiry.

Insulating gas and the EU F gas rules

SwitchgearPutting into operation with fluorinated gas in the insulating or breaking medium is prohibited from
Medium voltage, primary and secondary distribution, up to and including 24 kV1 January 2026
Medium voltage, primary and secondary distribution, above 24 kV up to and including 52 kV1 January 2030
High voltage, 52 kV up to and including 145 kV and up to 50 kA, gas with a global warming potential of 1 or more1 January 2028
High voltage, above 145 kV or above 50 kA, gas with a global warming potential of 1 or more1 January 2032

Regulation (EU) 2024/573, Article 13(9). The prohibition attaches to putting equipment into operation, not to when it was made, which matters for unused surplus stock. Taking switchgear out of operation in the Union and putting it into operation at another Union site is not treated as putting into operation (Article 13(10)). The regulation provides derogations tied to the outcome of a procurement procedure (Article 13(11) and 13(12)). Whether a derogation applies to a project is a question for the project, not for this page.

Applicable standards

StandardWhat it covers
IEC 62271-1Common specifications for AC switchgear and controlgear above 1000 V
IEC 62271-200AC metal enclosed switchgear and controlgear above 1 kV up to and including 52 kV
IEC 62271-100AC circuit breakers above 1000 V, where the transformer feeder uses one
Regulation (EU) 2024/573Restrictions on fluorinated gases in new switchgear, see below

The standard that applies is set by the specification and the destination market. Editions change, so the edition cited in a specification is confirmed in the quotation.

Documents normally requested

DocumentWhat it evidences
Technical datasheet and single line diagramRatings, panel functions and the arrangement offered
General arrangement drawingFootprint, height, cable entry and floor fixings
Type test reportThe design has passed the type tests of its standard, including internal arc where claimed
Routine test reportThe individual assembly's tests before dispatch
Schematic and wiring diagramsControl, protection and interlocking circuits
Operating and maintenance manualOperation, interlocks and maintenance

An internal arc classification is only as good as the type test behind it, and it applies to the tested configuration. Ask for the report that matches the arrangement offered.

What we need to quote accurately

01Rated voltage and network voltage
02Configuration: number of ring switches and transformer feeders, and whether it must be extensible
03Transformer rating and the protection type wanted on its feeder
04Insulation medium, and any destination restriction on fluorinated gas
05Manual or motorised operation, and any remote control or monitoring
06Cable type and connection arrangement
07The network operator's specification, where the unit will be adopted
08Quantity, destination, required delivery date and acceptable condition

Delivery and logistics

Distribution equipment is heavy, and a delivery date is only real once the site is ready for it. The dimensions and weight of the unit offered decide the vehicle, the lifting equipment and the route to the foundation, and they come from the manufacturer's drawing rather than from the rating.

Liquid immersed transformers are usually shipped filled, which affects transport rules and the handling on arrival. Anything crossing a border also carries customs documentation, and where the destination applies its own conformity or energy efficiency rules the paperwork has to match that market rather than the country of manufacture.

Lead times vary widely with rating, specification and manufacturer loading. We state a delivery basis in each quotation for the specific unit offered and do not publish a general lead time we cannot hold.

Common questions

Can a surplus or refurbished SF6 ring main unit be installed in the EU?

The EU prohibition on fluorinated gas in new distribution switchgear up to 24 kV attaches to putting the equipment into operation from 1 January 2026, not to its date of manufacture. Relocating switchgear that is already operating in the Union is treated differently. We check the insulation medium against the destination and the project before quoting any unit.

Related

Request a quote for this equipment

Send the rating, the voltage and the destination, or submit the specification, drawing or nameplate. Anything missing is raised before it reaches a supplier.